Construction of a new Wastewater Treatment Plant (WWTP) of 49,500 PE capacity with mechanical and biological treatment, sludge treatment and solar sludge drying.
Construction of about 3 km main collector sewer to the new WWTP
Construction of new sewer pumping station for connecting Gorica area to the sewer network by crossing the river via the Ura e Re bridge
Improvement and upgrading of the stormwater / sewer structure for separating stormwater from sewer network (construction of 7 sewer overflows (CSO 01 to CSO 07))
Overview of main works carried out under the WPIP / MIP V program
Key impact: new wastewater collection and treatment system assures clean environment