WPIP MIP V Investment Measures

UKR Fier - WPIP / MIP V investment measures

Drinking Water Supply works

  • Fier water network – supply and installation of ca. 22 km of pipes and about 1550 consumer connections
  • About 1,700 new individual water meters have been installed in Fier
  • Karafaj Well Field – Construction of new pumping station for all wells and rehabilitiation of intermediate reservoirs.
  • Major upgrade and improvement of SCADA system for monitoring and controlling wells and reservoirs as well as the network (reducing water loss and increasing revenues).

Waste Water System

  • Rehabilitation and new network – laying of over 8.5 km wastewater network and nearly 700 new network connections.
  • Construction of a new sewerage pumping station at Çeligrade